Gaelscoil Laighean

Gaelscoil Laighean

A Hybrid Modular School

A former council depot (brown field) site was the chosen location for this 876m² two storey Primary School.

Beginning March 2023 with a 24-week programme for all works to be completed before the end of August 2023; we executed the production management plan within our production facilities to complete this project within the tight timescale.

Planning granted on this project came with strict conditions; noise, dust and vibration monitoring carried out weekly.

Protection and monitoring of several trees identified on the site was carried out throughout the programme and finally, strict traffic monitoring and access control was provided.